United States Court of Federal Claims May 15, 2015, 11-129 (H. J. Lyness Construction, Inc. v. United States)

Also known as

United States · · · 15-05-2015

In the United States Court of Federal Claims

No. 11-129C

(Filed: May 15, 2015)

************************************

*

H.J. LYNESS CONSTRUCTION, INC., *

* Cross-Motions For Summary Judgment

Plaintiff, * On Damages

*

v. *

*

THE UNITED STATES, *

*

Defendant. *

*

************************************

OPINION AND ORDER

DAMICH, Senior Judge:

Plaintiff, H.J. Lyness Construction, Inc. (“HJL”), seeks damages stemming from the

termination for convenience by the General Services Administration (“GSA”) of HJL’s contract

to renovate and provide security improvements to the lobby of a federal building in Cincinnati,

Ohio. Previously, this Court determined that Plaintiff’s claims for its settlement costs were not

barred. Defendant then conceded liability. The case is now before the Court on the issue of

damages. For the reasons set forth below, Defendant’s Motion for Summary Judgment is

granted with correction for a clerical error.

I. Facts

On August 15, 2006, HJL entered into Contract No. GS05P06SLC3014 with GSA.

Compl. at ¶ 2. The contract was a firm-fixed price contract in the amount of $1,830,000 for

lobby renovations and security improvements to the John Weld Peck Federal Building in

Cincinnati, Ohio. Id. The performance bond, certificate of insurance and security clearances

were thereafter reviewed and approved by GSA and on November 9, 2006, GSA issued the

initial notice to proceed (“NTP”). Appendix to the Defendant's Cross-Motion for Summary

Judgment and Response to Plaintiff's Motion for Partial Summary Judgment ("DA") 5.

However, the NTP was rescinded by GSA on November 16, 2006, due to issues with the fire

evacuation plan associated with the contract design. DA 159. The parties agree that in the brief

period of time between when the NTP was issued and when it was rescinded, no performance of

1

the contract occurred. 1 Affidavit of Carl P. Meglan at 6. The contract was ultimately terminated

for convenience on April 6, 2009. DA 65-68.