IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

DIVISION II

CHAMBERS CREEK LLC, a limited liability No. 46898-1-II

company registered to do business in

Washington,

Appellant,

v.

CHARLES SCHMIDT; and ANTHONY UNPUBLISHED OPINION

SCHMIDT,

Respondents.

JOHANSON, C.J. — Chambers Creek LLC (Chambers) appeals the trial court’s order

granting summary judgment to Anthony and Charles Schmidt (collectively the Schmidts) on

Chambers’ claims for civil conspiracy and conversion. Chambers argues that summary judgment

was improper because its settlement agreement with Coyote Excavating, Inc. (Coyote) does not

preclude its claims against the Schmidts and there are genuine disputes of material fact. In

response, the Schmidts argue that Chambers’ claims are barred by judicial estoppel and the

compulsory counterclaims doctrine.

We hold that (1) neither judicial estoppel nor the compulsory counterclaim doctrine bar

Chambers’ conspiracy and conversion claims, (2) Chambers’ settlement agreement with Coyote

does not preclude its claims against the Schmidts, (3) a genuine dispute of material fact exists such

No. 46898-1-II

that summary judgment was improper on Chambers’ conversion claim, but (4) summary judgment

was proper on the civil conspiracy claim. Therefore, we affirm summary judgment on the civil

conspiracy claim and reverse summary judgment and remand for trial on the conversion claim.

FACTS

I. 2011 NEGLIGENCE ACTION

In February 2010, Chambers contracted with Coyote for the demolition phase of a project

owned by Chambers at a former paper mill. Anthony1 was the principal of Coyote. Coyote

subcontracted much of the labor for the project to Dennis Zyph, an employee of Mica Creek

Custom Homes LLC. Coyote demolished several structures that contained asbestos,

contaminating large portions of the project site. In April 2011, Coyote quit Chambers’ demolition

project and left its equipment on Chambers’ property.