Court of Appeals of Arkansas April 15, 2015, No. CV-14-592 (Travelers Casualty & Surety Co. of America v. Cummins Mid-South, LLC)
Also known as
United States · · · 15-04-2015
BART F. VIRDEN, Judge
h Travelers Casualty and Surety Company of America (Travelers) and Tycor Industries LLC (Tycor) appeal the circuit court’s order for Tycor to pay Cummins Mid-South LLC (Cummins) $59,115.14 plus costs, interest, and attorney’s fees on the grounds that (1) the language of the lien release was ambiguous, (2) Cummins did not waive its right to recover on the bond, and (3) Tycor was unjustly enriched. This appeal follows.
On appeal, Tycor asserts that the terms of the release were unambiguous, and that Cummins waived its right to payment under the bond by signing the release. Additionally, Tycor asserts that Cummins is not entitled to recover under the doctrine of unjust enrichment because the existence of a contract bars such recovery. We agree, and we reverse the circuit court’s order.
|⅞1. Facts
Tycor, a general contractor, bonded by Travelers, subcontracted with ARC Electrical (ARC) for installation and electrical work on the Armed Forces Reserve Center project (project). ARC purchased a generator from Cummins. ARC began to have problems performing, and Tycor fired ARC before the job was completed. On August 3, 2011, John Virden1 of Tycor contacted Nick Grandison, a project manager at Cummins, to ascertain if any money was owed for supplies relating to the project. Initially, Grandison ■ told Virden that Cummins was paid in full. However, on September 20, 2011, Cummins contacted Tycor and explained that it had made a mistake and their records showed that Ty-cor actually owed $59,115.14 for the generator. It was undisputed that Tycor had assumed the liabilities of ARC regarding this job. Tycor took no action. In November 2011, Tycor received written notice that a $2,748.16 bill from a September 2, 2011 service call on the generator had gone into collection. The invoice showed the date of the service call, the parts and labor charges, plus various charges related to the repair of the part.
Read the full text
This document is published by courtlistener.com.
Moonlit adds the citation network, article-level links and cross-references, which are available to search for free.
Sign in to Moonlit