New Mexico Supreme Court September 28, 2015, Docket No. S-1-SC-34768 (New Mexico Attorney General v. New Mexico Public Regulation Commission)

Also known as

United States · · · 28-09-2015

OPINION

CHÁVEZ, Justice.

{1} The Public Regulation Commission (PRC) granted Southwestern Public Service Company’s (SPS) application to (1) include a prepaid pension asset in its rate base in order for SPS to earn a return on this asset, and (2) obtain a renewable energy cost rider to recover approximately $22 million of renewable energy procurement costs from those customers who do not have a