Armed Services Board of Contract Appeals January 19, 2016, ASBCA No. 59043 (Al Nawars Company)

Also known as

United States · · · 19-01-2016

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- )

)

Al Nawars Company ) ASBCA No. 59043

)

Under Contract No. W9l7BE-06-C-OO18 )

APPEARANCE FOR THE APPELLANT: Mr. Buraier Yassen

Owner

APPEARANCES FOR THE GOVERNMENT: Thomas H. Gourlay, Jr., Esq.

Engineer Chief Trial Attorney

James D. Stephens, Esq.

Robert J. McKenney, Esq.

Engineer Trial Attorneys

U.S. Army Engineer District, Middle East.

Winchester, VA

OPINION BY ADMINISTRATIVE JUDGE O'SULLIVAN

DISMISSING WITH PREJUDICE FOR FAILURE TO PROSECUTE

This appeal arises from a contract awarded to appellant by a United States Army

Corps of Engineers contracting officer for a series of valve/pipe hardening projects in the

Iraqi Govemorate of Nineveh (R4, tab 4 at 1-4). The contract incorporated by reference

the standard Disputes clause, FAR 52.233-1, DISPUTES {JUL 2002)-ALTERNATE I

(DEC 1991) (R4, tab 4 at 10). 1 As discussed in our earlier decision denying the

government's motion to dismiss the appeal for lack of jurisdiction pursuant to the

Contract Disputes Act (CDA) six-year statute oflimitations, the government terminated

the contract for default; appellant subsequently submitted a monetary claim; and, upon

denial of the claim, appellant timely appealed to the Board. See Al Nawars Co., ASBCA

Nos. 59043, 59044, 15-1BCAif35,955.

By Order dated 29 January 2015, the Board directed the government to state its

views as to whether the contract had been issued pursuant to the Commanders'

Emergency Response Program (CERP), or was a procurement contract under the CDA.

The government responded, by letter dated 27 March 2015, with its view that the contract

was a CERP agreement. By Order dated 9 April 2015, the Board then directed the parties

1

The Disputes clause states that a "Contracting Officer's decision shall be final unless

the Contractor appeals ... as provided in the [CDA]." FAR 52.233-l(f). The CDA

provides that "[a] contractor, within 90 days from the date of receipt of a

contracting officer's decision ...