Ohio Court of Appeals January 23, 2017, 2016-L-043 (Xtreme Elements, L.L.C. v. Foti Contracting, L.L.C.)

Also known as

United States · · · 23-01-2017

[Cite as Xtreme Elements, L.L.C. v. Foti Contracting, L.L.C., 2017-Ohio-254.]

IN THE COURT OF APPEALS

ELEVENTH APPELLATE DISTRICT

LAKE COUNTY, OHIO

XTREME ELEMENTS, LLC, : OPINION

Plaintiff-Appellant, :

CASE NO. 2016-L-043

- vs - :

FOTI CONTRACTING, LLC, et al., :

Defendant-Appellee. :

Civil Appeal from the Lake County Court of Common Pleas, Case No. 2014 CV

000639.

Judgment: Affirmed in part, reversed in part, and remanded.

Matthew D. Gurbach, Thomas O. Crist, and Anthony C. Sallah, Benesch, Friedlander,

Coplan & Aronoff LLP, 200 Public Square, Suite 2300, Cleveland, OH 44114 (For

Plaintiff-Appellant).

John K. Lind, Jr., 3185 Belvoir Boulevard, Shaker Heights, OH 44122 (For Defendant-

Appellee).

DIANE V. GRENDELL, J.

{¶1} Plaintiff-appellant, Xtreme Elements, LLC, appeals from the Judgment

Entry of the Lake County Court of Common Pleas, ruling in favor of defendant-appellee,

Foti Contracting, LLC, on various claims following a trial. The issues to be determined

in this case are whether prejudgment interest must be paid under the Prompt Payment

Act when the parties present conflicting testimony about the soundness of certain

construction work and there is a dispute over whether payment was withheld in good

faith, and whether the court erred by failing to hold a hearing on attorney’s fees when

awarding prejudgment interest for a claim pursuant to the Prompt Payment Act. For the

following reasons, we affirm in part and reverse in part the decision of the lower court

and remand for further proceedings consistent with this opinion.

{¶2} On March 18, 2014, Xtreme filed a Complaint against Foti and Associated

Associates in the Lake County Court of Common Pleas, which was a refiling of a 2012

Complaint. The Complaint stated that Foti had a contract with Southington Local

School District for the construction of a school facility and that Xtreme had entered into

three subcontracts with Foti in August and October 2009 to perform concrete work for

that project.