Ohio Court of Appeals November 13, 2017, 13-07-04 (New Riegel Local School Dist. Bd. of Edn. v. Buehrer Group Architecture & Eng. Inc.)
Also known as
United States · · · 13-11-2017
[Cite as New Riegel Local School Dist. Bd. of Edn. v. Buehrer Group Architecture & Eng. Inc., 2017-
Ohio-8522.]
IN THE COURT OF APPEALS OF OHIO
THIRD APPELLATE DISTRICT
SENECA COUNTY
NEW RIEGEL LOCAL SCHOOL
DISTRICT, BOARD OF EDUCATION,
CASE NO. 13-17-04
PLAINTIFF-APPELLANT,
-and-
STATE OF OHIO,
PLAINTIFF-APPELLEE,
v.
OPINION
THE BUEHRER GROUP
ARCHITECTURE & ENGINEERING,
INC., ET AL.,
DEFENDANTS-APPELLEES.
Appeal from Seneca County Common Pleas Court
Trial Court No. 15 CV 0115
Judgment Affirmed in Part, Reversed in Part
Date of Decision: November 13, 2017
APPEARANCES:
Christopher L. McCloskey and Tarik Kershah for Appellant
Michael J. Valentine for Appellees, The Buehrer Group Architecture &
Engineering, Inc. and Estate of Huber H. Buehrer
Case No. 13-17-04
WILLAMOWKSI, J.
{¶1} Plaintiff-appellant New Riegel Local School District Board of
Education (“the School”) brings this appeal from the judgment of the Court of
Common Pleas of Seneca County granting the judgment on the pleadings filed by
defendants-appellants the Buehrer Group Architecture & Engineering, Inc. (“the
Group”), the Estate of Huber H. Buehrer (“the Estate”) (collectively known as “the
Buehrer Group”). For the reasons set forth below, the judgment is affirmed in part
and reversed in part.
{¶2} This case arises from the construction of a new Kindergarten through
12th Grade School Facility Project (“the Project”) built as part of the Ohio Classroom
Facilities Assistance Program. Doc. 2. As a result of the Project, the School entered
into contracts with multiple contractors starting in February of 2000. Id. One of
these contractors was the Buehrer Group. Id. The Group contracted with the school
to provide professional design services for the Project. Id. at Ex. A. The School
began occupying the school building on December 19, 2002, Doc. 88, Ex. K. The
State issued a Certificate of Completion transferring all of the interest of the State
in the project to the School on March 3, 2004. Doc. 24.