Court of Appeals of Tennessee November 27, 2017, M2016-02382-COA-R3-CV (Blue Water Bay At Center Hill, LLC v. Larry J. Hasty)

Also known as

United States · · · 27-11-2017

11/27/2017

IN THE COURT OF APPEALS OF TENNESSEE

AT NASHVILLE

August 15, 2017 Session

BLUE WATER BAY AT CENTER HILL, LLC, ET AL. v. LARRY J.

HASTY, ET AL.

Appeal from the Chancery Court for Williamson County

No. 43307 Deanna Johnson1, Judge

___________________________________

No. M2016-02382-COA-R3-CV

___________________________________

This appeal follows the trial court’s confirmation of an arbitration award. There are four

participating parties on appeal, the Appellant and three separate Appellees. With respect

to the claims asserted by Appellee Blue Water Bay against the Appellant, we hereby

vacate the trial court’s orders and remand for further proceedings because the trial court

erred in not allowing the Appellant pre-arbitration discovery regarding issues pertaining

to arbitrability. With respect to the claims involving the other two Appellees, we reverse

the trial court’s orders due to the absence of a sufficient basis to establish arbitrability.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Vacated in

part and Reversed in part and Remanded

ARNOLD B. GOLDIN, J., delivered the opinion of the Court, in which BRANDON O.

GIBSON and KENNY ARMSTRONG, JJ., joined.

Ben M. Rose and Joshua D. Arters, Brentwood, Tennessee, for the appellant, Larry J.

Hasty.

William B. Hawkins, III and Eric G, Evans, Nashville, Tennessee, for the appellees, Blue

Water Bay At Center Hill, LLC, and Edmond R. Queen.

Trajan Carney, Nashville, Tennessee, for the appellee, Greyhawk Development

Corporation.

1

Prior to arbitration, the case was presided over by the Honorable James G. Martin, III.

OPINION

BACKGROUND AND PROCEDURAL HISTORY

This case involves a dispute among the Appellant, Larry Hasty (“Mr. Hasty”), and

the Appellees, Blue Water Bay at Center Hill, LLC (“Blue Water”), Edmond Queen

(“Mr. Queen”), and Greyhawk Development Corporation (“Greyhawk”). The genesis of

the lawsuit lies in a 2007 loan granted to Greyhawk by Cadence Bank, N.A. (“Cadence”).