Superior Court of Pennsylvania February 9, 2018, 188 EDA 2017 (Myron R. Haydt Development v. 1691 Bethlehem Pike)

Also known as

United States · · · 09-02-2018

J-A28040-17

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37

MYRON R. HAYDT DEVELOPMENT, : IN THE SUPERIOR COURT OF

INC. : PENNSYLVANIA

:

:

v. :

:

:

1691 BETHLEHEM PIKE LP :

: No. 188 EDA 2017

Appellant :

Appeal from the Judgment Entered December 16, 2016

In the Court of Common Pleas of Bucks County Civil Division at No(s): No.

2014-80163

BEFORE: GANTMAN, P.J., PANELLA, J., and DUBOW, J.

MEMORANDUM BY DUBOW, J.: FILED FEBRUARY 09, 2018

Appellant, 1691 Bethlehem Pike LP, appeals from the December 16,

2016 Judgment entered in the Bucks County Court of Common Pleas in favor

of Appellee, Myron R. Haydt Development, Inc., in accordance with a verdict

rendered after a non-jury trial. After careful review, we affirm.

Appellant, a strip mall owner, and Appellee, a contractor, entered into

a written construction contract.1 The construction contract provided that

Appellee would perform façade renovation and site improvement services at

Appellant’s strip mall located in Hatfield Township, Montgomery County, at a

____________________________________________

1 Appellant’s general partner, Scott Hartzell, and Appellee’s principal, Myron

R. Haydt, signed the contract on behalf of their respective businesses.

Although they are not individually named as parties, to facilitate our

discussion we herein refer to them as Appellant and Appellee, respectively.

J-A28040-17

cost of $573,000, to be paid by Appellant. The contract included, inter alia,

a “no oral modifications” clause. It also initially provided 120 days for

completion of the project2 and that Appellee would not receive final payment

until it delivered subcontractor lien waivers to Appellant.

It is undisputed that Appellee did not complete work on the project

because Appellant asked it to leave the job site. However, at the time

Appellant terminated Appellee, Appellee had substantially completed work

on the underlying contract and only minor punch-list tasks remained

unfinished.