Superior Court of Pennsylvania February 9, 2018, 188 EDA 2017 (Myron R. Haydt Development v. 1691 Bethlehem Pike)
Also known as
United States · · · 09-02-2018
J-A28040-17
NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37
MYRON R. HAYDT DEVELOPMENT, : IN THE SUPERIOR COURT OF
INC. : PENNSYLVANIA
:
:
v. :
:
:
1691 BETHLEHEM PIKE LP :
: No. 188 EDA 2017
Appellant :
Appeal from the Judgment Entered December 16, 2016
In the Court of Common Pleas of Bucks County Civil Division at No(s): No.
2014-80163
BEFORE: GANTMAN, P.J., PANELLA, J., and DUBOW, J.
MEMORANDUM BY DUBOW, J.: FILED FEBRUARY 09, 2018
Appellant, 1691 Bethlehem Pike LP, appeals from the December 16,
2016 Judgment entered in the Bucks County Court of Common Pleas in favor
of Appellee, Myron R. Haydt Development, Inc., in accordance with a verdict
rendered after a non-jury trial. After careful review, we affirm.
Appellant, a strip mall owner, and Appellee, a contractor, entered into
a written construction contract.1 The construction contract provided that
Appellee would perform façade renovation and site improvement services at
Appellant’s strip mall located in Hatfield Township, Montgomery County, at a
____________________________________________
1 Appellant’s general partner, Scott Hartzell, and Appellee’s principal, Myron
R. Haydt, signed the contract on behalf of their respective businesses.
Although they are not individually named as parties, to facilitate our
discussion we herein refer to them as Appellant and Appellee, respectively.
J-A28040-17
cost of $573,000, to be paid by Appellant. The contract included, inter alia,
a “no oral modifications” clause. It also initially provided 120 days for
completion of the project2 and that Appellee would not receive final payment
until it delivered subcontractor lien waivers to Appellant.
It is undisputed that Appellee did not complete work on the project
because Appellant asked it to leave the job site. However, at the time
Appellant terminated Appellee, Appellee had substantially completed work
on the underlying contract and only minor punch-list tasks remained
unfinished.