Court of Appeals for the Sixth Circuit March 11, 2019, 18-1958/1995 (Am. Mun. Power, Inc. v. Nat'l Labor Relations Bd.)
Also known as
United States · · · 11-03-2019
RECOMMENDED FOR FULL-TEXT PUBLICATION
Pursuant to Sixth Circuit I.O.P. 32.1(b)
File Name: 19a0040p.06
UNITED STATES COURT OF APPEALS
FOR THE SIXTH CIRCUIT
AMERICAN MUNICIPAL POWER, INC., ┐
Petitioner/Cross-Respondent, │
│
> Nos. 18-1958/1995
v. │
│
│
NATIONAL LABOR RELATIONS BOARD, │
Respondent/Cross-Petitioner. │
┘
On Petition for Review and Cross-Application for Enforcement
of an Order of the National Labor Relations Board;
No. 10-CA-221403.
Decided and Filed: March 11, 2019
Before: SUTTON, WHITE, and DONALD, Circuit Judges.
_________________
COUNSEL
ON BRIEF: Kerry P. Hastings, Conor H. Meeks, TAFT STETTINIUS & HOLLISTER LLP,
Cincinnati, Ohio for Petitioner/Cross-Respondent. Linda Dreeben, Julie B. Broido, Milakshmi
V. Rajapakse, NATIONAL LABOR RELATIONS BOARD, Washington, D.C., for
Respondent/Cross-Petitioner.
_________________
OPINION
_________________
SUTTON, Circuit Judge. When American Municipal Power opened a power plant in
Smithland, Kentucky, the International Brotherhood of Electrical Workers petitioned to represent
the plant’s operators. The National Labor Relations Board certified a bargaining unit consisting
of the full-time and regular part-time operators employed at the newly opened facility. Because
Nos. 18-1958/1995 Am. Mun. Power, Inc. v. NLRB Page 2
the company worries that this definition includes operators based at other locations that it
temporarily assigns to Smithland, it asked the Board to modify the bargaining unit’s language to
exclude temporary assignees. The Board disagreed. It saw no need to make the clarification
under the circumstances. We deny the company’s petition and enforce the Board’s order to
negotiate.
At American Municipal Power’s hydroelectric plants, operators run the generating units,
coordinate the flow of water, and conduct maintenance. As the Smithland plant came online in
2017, the company sent four operators from its Cannelton Dam facility in Hawesville, Kentucky
to the Smithland facility.